By David Laguerre
Work starts at High Falls Terrace while environmental review continues for the larger Rochester riverfront park.
Construction has begun on the first phase of High Falls State Park in Rochester, opening a new stage in a project meant to turn former industrial riverfront land into public space. The November 18 groundbreaking at the former Terrace Park site is a construction milestone, not the opening of the full park.
Gov. Kathy Hochul’s announcement says Rochester licensed the terrace property to the state this month. New York has committed $8 million for design and $75 million for the park’s first phase. A portion of that first-phase funding will support terrace improvements.
The larger effort will unfold as environmental cleanup and site restoration advance. The governor’s office says cleanup work could continue for up to five years, with more areas opening in stages. State Parks does not plan to charge vehicle-use fees.
What the first phase would provide
The High Falls Terrace design places accessible overlooks, a nature-themed play area, a gathering lawn, restrooms, shaded picnic space and a small parking area at the gateway to the future park. The playground design includes a tower, slides and a climbing wall.
Those are planned amenities, not a list of facilities visitors can use today. The terrace is intended to connect downtown neighborhoods with later improvements in the lower Genesee River gorge.
A Heritage Walk would explore immigration and migration to Rochester through people’s memories, daily lives and hopes for their families. The design team says that work should be developed with community organizations and local experts, with stories tied to the actual site rather than generic historical displays.

Why the cleanup matters
The project’s public timeline traces the park proposal to 2022 and the start of cleanup near the former Beebee Station to 2023. It records completion of remediation at the RG&E West Station manufactured-gas-plant site in June 2025, while work on other parcels continues.
Older gas-making operations left coal-tar contamination that can affect soil, groundwater and river sediment, according to the governor’s announcement. That history helps explain why a groundbreaking at one gateway does not mean the entire gorge is ready for public access.
The project website describes a roughly 40-acre park. However, the state’s November 11 environmental notice describes a broader proposed action covering approximately 85 acres in and around the falls and gorge. Readers should not treat those figures as interchangeable. The current review describes a larger area than the older park summary, and the precise final footprint remains part of the planning process.
A larger plan still under review
The November 4 draft scoping document proposes about five miles of paved paths, six overlooks and two new pedestrian bridges. It also discusses restrooms, maintenance and police facilities, and adapting the existing Water Works Building for visitor support.
The proposed construction sequence moves north in phases, expanding access as areas connect. These are proposals being examined, not a promise that every feature has final approval or a firm opening date.
State Parks determined that the broader project could have significant environmental effects and requires a draft environmental impact statement. Public scoping helps decide which impacts, alternatives and ways to reduce harm that study must address. It is an opportunity to ask specific questions about access, riverfront habitat, construction and long-term operations.
How to comment or join a meeting
The state’s environmental notice lists two virtual scoping sessions: November 30 at 11 a.m. and December 1 at 6 p.m., local New York time. Registration is due November 24. Email HighFalls.Plan@parks.ny.gov with your name, title and organization to request registration. The draft scope says login information will be sent by November 25.
Written comments are accepted through December 6 at the same email address, or by mail to Evyn Iacovitti, 3160 DeVeaux Woods Drive, Niagara Falls, NY 14305. For communication accommodations, contact Owen Gilbo at Owen.Gilbo@parks.ny.gov or 518-402-2648. Review the official notice before registering for any updated instructions.
What Mohawk Valley readers should know
This is a Rochester project, not a new park in Utica or the Mohawk Valley. Its immediate value for interested readers is a chance to follow how state-funded riverfront reuse balances recreation, industrial cleanup and public access. For a future visit, follow the project’s updates rather than assuming the whole park is open because construction has started.
Follow more New York State news from Mohawk Valley Voice.