The contract covers structural repairs, stairways, platform edges and historic finishes. A construction start date and any service changes were not announced.
The Metropolitan Transportation Authority board approved a roughly $119 million contract to rehabilitate the Chambers Street subway station, which serves the J and Z lines in Lower Manhattan, amNewYork reported Nov. 18. Gov. Kathy Hochul’s office said the project would tackle water damage and structural decay at the station, which opened in 1913.
The contract goes to a joint venture of Forte Construction Corp. and Citnalta Construction Corp., according to the governor’s announcement. It is a design-build contract, which puts design and construction under one agreement. The state’s announcement did not give a construction start or completion date, or say which trains or entrances, if any, will be affected while work is underway.
What the Chambers Street subway station rehab covers
The state listed repairs to structural steel and concrete, work to address leaks and improve ceilings, rebuilding stairs and replacing platform edges.
The plan also calls for new lighting and security cameras, floor finishes in some mezzanine areas, paint and new artwork. This is more than a cosmetic cleanup: the work includes parts of the station riders rely on to reach, wait for and board trains.
As part of the rehabilitation, the agency plans to replace damaged finishes and preserve historical features, including mosaics, ceramic tilework and terra cotta details. The governor’s office said the station is listed on the National Register of Historic Places and serves 18,196 passengers on an average weekday.

What’s separate from the station contract?
The governor’s office also described a study that involves the larger Chambers Street and Brooklyn Bridge–City Hall complex. Researchers are examining whether excess heat from the complex could help heat nearby municipal buildings in winter through a thermal energy network. That is a separate effort being studied in coordination with the station work.
The rehabilitation announcement does not mean the proposed network has been approved for installation.
The state also discussed a separate contract for accessibility and repair work at three other stations: 110 St on the 6, 145 St on the A/B/C/D, and Wakefield–241 St on the 2. Those station upgrades are not part of the $119 million Chambers Street package.
The list of improvements for Chambers Street does not specify new elevators. Riders who need step-free travel should check the MTA’s accessible-station information when planning a trip.
Where the money comes from
The governor’s office said congestion-pricing revenue made the work possible through the MTA’s 2020–24 capital program. That budget label describes the investment program paying for the project; it does not mean the work was completed by 2024.
The state says congestion pricing is generating $15 billion for the entire capital plan. The Chambers Street contract is one project within that larger program, not a second $15 billion spending commitment.
For people traveling from the Mohawk Valley to Lower Manhattan, the practical question is whether a particular station or entrance is usable on the day of the trip. The contract approval alone does not answer it. Check the MTA’s J/Z line information and current service alerts before choosing a route, and look for posted elevator notices if step-free access is essential.
Watch for a start date, planned detours and details on which stairways will remain open.
The MTA timetable describes Z trains as part of rush-hour skip-stop service, so do not assume the J and Z are interchangeable throughout the day.
Not every subway repair requires the same kind of service change. Our earlier coverage of the completed Far Rockaway station repairs describes a separate project. It should not be used to infer a closure schedule for Chambers Street.
Sources: Governor’s Nov. 18 announcement; amNewYork’s board-approval coverage; MTA line information.